ADU Permits And Timeline

Last updated

California law gives a city or county 15 business days to tell you in writing whether your ADU application is complete, then 60 days from a complete application to approve or deny it when a home already stands on the lot (Government Code section 66317). State law does not set how long design or construction takes.

The Review Deadlines In State Law

These come from the HCD ADU Handbook (March 2026) and the cited Government Code sections.

A new house and an ADU submitted together can be reviewed together. The ADU application is considered without discretionary review or a hearing.

Typical Steps

  1. Feasibility. Confirm zoning, lot size, setbacks, utilities, and any special area rules.
  2. Design. A designer or architect draws site and floor plans. Some cities publish ready-made plans you can start from.
  3. Submit. File plans, forms, and fees with the planning and building departments.
  4. Corrections. Reviewers send comments. Answer them quickly and completely.
  5. Permit issued. Pay remaining fees and begin work.
  6. Inspections. The city inspects foundation, framing, plumbing, electrical, and final.
  7. Certificate of occupancy. Required before anyone moves in.

Pre-Approved Plans

State law required each local agency to set up a program to pre-approve ADU plans by January 1, 2025, and to post the approved plans on its website (Government Code section 65852.27). Using a pre-approved plan can shorten plan review, but your site still needs its own review. Examples are in our city guides, such as Los Angeles and Sacramento.

What Varies And Why

Ask each builder for a written schedule with start and finish dates for each phase, and for what happens if the schedule slips. See Questions To Ask An ADU Builder.

Help When A City Is Not Following The Law

The handbook says to work with the permitting agency first. HCD offers technical assistance after an application is submitted, through the portal on its HCD ADU page.

This page is general information, not legal or financial advice. Rules and prices change. Confirm details with your city or county building department and a qualified professional.

Related guides: California ADU Rules, ADU Cost In California.

Common Questions

How long does a city have to approve an ADU permit in California?

The permitting agency must approve or deny a complete application within 60 days when a single-family or multifamily home already exists on the lot (Government Code section 66317). A new house and an ADU submitted together can be reviewed together.

What happens if the city does not respond about my ADU application?

An application is deemed complete if the agency does not issue a written completeness determination within 15 business days (Government Code section 66317, per the HCD handbook).

What if my ADU application is denied?

A denial must come with a full set of written comments listing what is defective and how to fix it, within the same 60 days. If an application is found incomplete or denied, the agency must offer an appeal process with a written decision within 60 business days of the appeal.